CVD Furnaces

Chemical vapor deposition equipment for C/C composite processing. The graphite hot zone, gas delivery and vacuum system are configured around your preforms and deposition cycle.

Deposition for Carbon-Based Composites

During chemical vapor deposition, a carbon-bearing process gas enters the heated work zone and decomposes to deposit carbon. The preform, gas chemistry, temperature and pressure cycle determine the equipment and process requirements.

Our CVD furnaces are designed for carbon-based composites, including C/C friction components. A vertical furnace configuration combines graphite resistance heating, nitrogen and natural-gas connections, and controlled low-pressure operation.

Vertical arrangements Top or bottom access is configured around the load and handling method. The reference furnace uses top unloading and an access platform.
Horizontal arrangements Single- or double-door layouts can be discussed for horizontal loading and unloading, based on the workpiece and site layout.
Angled view of a vertical deposition furnace with stairs, platform and front control cabinet Vertical CVD furnace with an access platform, process pipework and control cabinets.

An Integrated Deposition System

The chamber, hot zone, gas circuit and vacuum equipment work together around the deposition process.

Chamber & Graphite Hot Zone

The reference furnace has a double-wall 304 stainless-steel chamber, graphite resistance heating, a graphite inner cylinder and carbon-felt insulation. The chamber, lid and electrode connections incorporate cooling circuits.

Measured Gas Delivery

A process-gas mass-flow controller works with nitrogen flow measurement and a mixing vessel. Gas enters the graphite chamber from below through a distribution plate.

Vacuum & Tar Filtration

Two rotary-vane pumps, vacuum valves and pressure measurement support the reference system. A tar collector in the vacuum line collects condensable vapors and particles upstream of the pumps.

Process & Equipment Interfaces

Gas supply, vacuum capacity, filtration access and the discharge connection are selected around the process chemistry. The project scope identifies the interface to site exhaust treatment.

Control, Monitoring & Protection

Recipes & Process Records

Programmed temperature ramps and holds can run automatically with manual control available. The touchscreen system can record and export temperature, vacuum and pressure-rise data.

Cooling-Water Monitoring

A closed-loop water circuit serves the chamber, lid, electrode connections and vacuum equipment. Pressure monitoring and return-flow indication help track cooling-water availability.

Equipment Interlocks

The reference design includes checks for lid closure and vacuum before heating, plus temperature-sensor, overtemperature, cooling-loss and pressure alarms or interlocks. Protection settings are defined for the final process.

Reference Configuration & Technical Data

The values below apply to this vertical furnace configuration. Working dimensions, process limits and acceptance criteria are agreed for each project.

Vertical CVD Furnace

Effective work zone Ø 600 × 600 mm (diameter × height)
Maximum stated batch load 300 kg
Heating system Graphite resistance heating
Reference heating power 120 kW
Reference process-pressure control 700–2,000 Pa
Ultimate pressure ≤ 10 Pa, empty chamber in cold condition
Pressure-rise rate ≤ 6.7 Pa/h, empty chamber in cold condition
Pump-down time to ultimate pressure ≤ 30 min, empty chamber in cold condition
Specified work-zone uniformity ±10 °C
Process-gas connections Nitrogen and natural gas

Process temperature, pressure reference and temperature-performance test conditions are confirmed in the project specification.

Configuration Scope

Parts & material Preform shape, dimensions, fixture arrangement, load mass and the required deposition process.
Thermal system Hot-zone dimensions, temperature range, measurement system, ramp and hold requirements, and heating power.
Gas & vacuum Precursor composition, flow-control range, process pressure, pumping duty, tar collection and exhaust interfaces.
Factory integration Door or lid movement, loading clearance, platforms, service access, cooling water, electrical supply and controls.

Request a project specification →

Specifications for Your CVD Furnace

The furnace specification covers your deposition conditions, gas supply and exhaust connections.

Deposition temperature range Maximum operating temperature & measurement system Process gas composition & calibrated flow range Deposition target, cycle time & test method Exhaust-treatment scope & site interfaces

Inspection, Installation & Documentation

Inspection & Acceptance

Factory inspection can cover the chamber, cooling circuit, cold vacuum, pressure-rise rate, pump-down time and electrical system. Site commissioning and loaded trial runs form part of the agreed acceptance scope.

Site Preparation

The installation layout defines the foundation, lifting and access requirements. The technical scope allocates responsibility for power, process gases, cooling water, exhaust connections and interconnecting cables.

Drawings & Operating Records

Project documentation can include layout and installation drawings, system and electrical diagrams, operating instructions, wear-parts information and an equipment conformity certificate. Operator and maintenance training is defined with commissioning.

Discuss Your Deposition Process